The Street Sales Tax Advisory Committee has developed a preliminary list of projects for consideration for the 2017 Street Sales Tax program. Augusta’s City Engineer Schwab Eaton will be on site in these neighborhoods evaluating the preliminary list of streets. These onsite evaluations began Friday and will continue through Feb. 9. Schwab will have employees, vehicles and equipment on the designated streets checking pavement conditions in order to update construction cost estimates. These estimates will be presented to the Street Sales Tax Committee at the second public hearing scheduled for 6:30 p.m. Feb. 9 at City Hall.

Potential project areas are : Lakeside II Addition; Woodland Drive (Ohio to Ridgecrest); Ranchwood Drive (Ohio to Ridgecrest); Huntington Rd (Ohio to Ridgecrest); Ridgecrest (Woodland to Huntington); Post Rd (Woodland to Ranchwood); Brookdale Rd (Ranchwood to Huntington); Angelina Drive; Yellowrose Lane; Limerick Lane; Kelly Ave (Ohio St. to Kelly Ct.); Ridgewood Drive; and Cedar Lane.